•  Timeline

    East Ramapo Central School District Capital Improvements Plan

    ARPA Construction Monthly Update August 2023_2

    ARPA Construction Monthly Update August 2023

    ARPA Construction Monthly Update July 2023

    ARPA Construction Monthly Update June 2023

    ARPA Construction Monthly Update - April 2023

    ARPA Construction Monthly Update - March 2023

    ARPA Construction Monthly Update - February 2023

    Construction update report - July, 2022


    Construction Update - June 2022 BOE Update

    Board of Education Construction Update - May 2022

     

    The American Rescue Plan Elementary and Secondary Emergency Relief Fund (ARP-ESSER) is providing over $90,000,000 to East Ramapo Central School District. About eighty percent of this funding is being recommended to fund capital projects which will improve instructional and non-instructional spaces, such as lighting and ceiling replacement, electrical systems, windows doors and ventilation. This is the estimated 3-year timeline for completing these facilities upgrades. 

    2021

    2021 Emergency Capital Improvement Projects 

    CRMS CougarChestnut Ridge Middle School Abatement Project 

    Chestnut Ridge Floors

    Spring Valley Tiger Spring Valley High School Abatement Project 

    • Hazardous Materials Abatement (VAT) Abate VAT flooring building-wide.
    • New Flooring (LVT)

    The Spring Valley High School capital improvement project is well underway and remediation is on schedule to be completed by December 23, 2021 with the anticipated return to in-person instruction for students on January 3, 2022. READ MORE.

    Spring Valley HS Abatement

    Phase 1

    Phase I: Summer of 2022

    •  

    PanthersPomona Middle School

    • Hazardous Materials Abatement (VAT) Abate VAT flooring building wide.
    • New Flooring (LVT).
    • Kitchen Hoods Replacement.

    ElmwoodElmwood Elementary School

    • Hazardous Materials Abatement (VAT).
    • New Flooring (LVT).
    • Kitchen Hoods Replacement.
    • Window/Storefront Replacement (Replace Original Window System) – Not Summer work


    Kakiat LogoKakiat STEAM Academy

    • Hazardous Materials Abatement (VAT) Replace remaining original window systems.
    • New Flooring (LVT)
    • Kitchen Hoods Replacement.
    • Window/Storefront Replacement (Replace Original Window System) – Not Summer work

    Margetts LogoMargetts Elementary School

    • Hazardous Materials Abatement (VAT) Abate all VCT laid on top of VAT flooring building wide.
    • New Flooring (LVT)
    • Kitchen Hoods Replacement.
    • Window/Storefront Replacement (Replace Original Window System) – Not Summer work

    Hempstead logoHempstead Elementary School

    • Kitchen Hood Replacement.

    CRMS LogoChestnut Ridge Middle School

    • Kitchen Hood Replacement

    Phase II

    Phase II: Summer of 2023

    CRMS LogoChestnut Ridge Middle School

    • Replace non-operating chiller.
    • Chiller Sound Mitigation
    • ADA Compliance Provide ADA compliant toileting and other upgrades
    • Window/Storefront Replacement (Replace Original Window System) – Not Summer work

    PanthersPomona Middle School

    • Air Handling Unit Replacement (Gym, Café, Lockers)
    • Air Handling Unit Replacement (Music, Corr., Back Gym)
    • Air Handling Unit Replacement (Offices)
    • ADA Compliance Provide ADA compliant toileting and other upgrades.
    • Window/Storefront Replacement (Replace Original Window System) – Not Summer work

    Eldorado LogoEldorado Elementary School

    • Unit Ventilaor Replacement
    • Unventilated - Office / Small Space
    • Hazardous Materials Abatement (VAT)
    • New Flooring
      ADA Compliance Provide ADA compliant toileting and other upgrades. 
    • Kitchen Hoods Replacement.

    Window/Storefront Replacement (Replace Original Window System) - Not Summer Work

    Fleetwood Logo  Fleetwood Elementary School

    • Unit Ventilator Replacement
    • Unventilated - Office / Small Space
    • Unventilated - Classroom
    • Air Handling Unit Replacement
    • Hazardous Materials Abatement (VAT) Remove damaged VAT in gymnasiums.
    • Window/Storefront Replacement (Replace Original Window System) - Not Summer Work
    • New Flooring (LVT) Replace all removed flooring.
    • Window Treatments
    • ADA Compliance Provide ADA compliant toileting and other upgrades.
    • Kitchen Hoods Replacement

    Grandview GatorGrandview Elementary School

    • Unit Ventilator Replacement
    • Unventilated - Office / Small Space
    • Unventilated - Classroom
    • Air Handling Unit Replacement
    • Hazardous Materials Abatement (VAT)
    • New Flooring (LVT)
    • Built-in Shelving
    • Window / Storefront Replacement
    • Window Treatments
    • ADA Compliance Provide ADA compliant toileting and other upgrades.

    Summit Park LogoSummit Park Elementary School

    • Unit Ventilator Replacement
    • Unventilated - Office / Small Space
    • AHU Replacement
    • Hazardous Materials Abatement (VAT) 
    • New Flooring (LVT)
    • Window / Storefront Replacement Replace remaining original window systems. Not Summer work.

     

    Hempstead logoHempstead Elementary School

    • Unit Ventilator Replacement
    • Unventilated - Office / Small Space
    • Hazardous Materials Abatement (VAT) Abate all VCT laid on top of VAT flooring at the first floor.
    • New Flooring (LVT)
    • ADA Compliance Provide ADA compliant toileting and other upgrades.
    • Window / Storefront Replacement Replace remaining original window systems. Not Summer work.

    Lime Kiln LogoLime Kiln Elementary School

    • Unit Ventilator Replacement
    • Hazardous Materials Abatement (VAT) Abate VAT flooring in Gymnasium
    • Flooring Removal (VCT) Remove splitting and damaged VCT in various classrooms.
    • New Flooring (LVT)
    • Kitchen Hoods Replacement
    • Window / Storefront Replacement Replace remaining original window systems. Not Summer work.